Sunday, August 29, 2010

Brickwork continued .....

Brickwork half way up around house.  Garage boundary wall up. Wiring in.  Heating/cooling ducts in and heating/cooling unit in ceiling. 

Front pier on left is fully bricked (this will be rendered)

Lots of rain means we get a free swimming pool in front and backyards!

Garage boundary wall

Sunday, August 22, 2010

Brickwork

Rain delayed starting of brickwork.  Brickies were on site Friday.

Thursday, August 5, 2010

Wrapping our big present

House wrap is almost finished. The front balcony sliding door has been installed. Brickwork to commence next week.